  • Installation of Mechanical roof plant including 500 tonne crane lift for 2 chillers, 2 heaters, 7 air handling plant.
  • Installation of roof mounted plant room including pipework and supports, BMS panel for control and pump installation for CHW and LTHW.
  • Roof mounted generator sets including generator synchronisation and roof mounted control panel.
  • Infrastructure bus bar throughout the building in both cast resin and standard steel encased copper.
  • Installation of HV transformers and LV switch gear throughout the basement and risers including two UPS rooms and four major switch panels with automatic control and EMS systems.
  • Fit out of four studios including power supplies, lighting, chilled beams and air systems.  Fit out of specialist office space including control rooms for the studios and general office space.
  • Fit out of dressing rooms for celebrities and presenters.
  • Fit out of kitchen and restaurant areas for both staff and studio cooking.

 

Project value: £11.5m

Contract duration: 36 weeks

Area: 12,742 m sq

Main Contractor: Como