  • Fit out of office space on levels three and two including surface services for ductwork and pipe in a space made from two existing building joined together by a new build at the rear.
  • Installation studios on level 1 and ground floor.
  • Installation of reception and Bar on ground floor.
  • Installation of toilet block and storage space within basement.
  • Roof and roof plant room installation of DX Chiller and VRV systems plant to supply the cooling throughout the building.
  • Heating system installation VIA DX and hot water cylinders in the basement plus modifications to the electrical panels and supplies from EDF to serve the distribution network throughout the floors.

 

Value: £1.4m

Contract duration: 30weeks

Area: 3060 sq2

Main Contractor: Parkeray